← Back to map

Little Goose

Columbia County, Washington · EIA plant ID 3926 · Operator: USACE Northwestern Division
HydroConventional HydroelectricBA: BPAT
Nameplate810MWSummer 810 MW
Generators6in service
Net generation1,563GWh12 mo to Aug 2026
Capacity factor22%hydro units, summer MW
Heat rate—thermal plants only
First online1970

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2005201020152020202522.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20011,818.622.3%—
20021,98524.3%—
20032,165.626.5%—
20042,219.931.2%—
20051,832.525.8%—
20062,633.637.1%—
20071,702.824.0%—
20082,154.130.3%—
20092,312.832.6%—
20101,88126.5%—
20112,89340.8%—
20122,302.432.4%—
20131,691.923.8%—
20142,224.631.4%—
20151,709.324.1%—
20162,039.528.7%—
20172,813.439.6%—
20182,452.134.6%—
20192,101.729.6%—
20201,685.523.7%—
20211,34619.0%—
20221,619.322.8%—
20231,559.222.0%—
20241,441.720.3%—
20251,589.322.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY135135Apr 1970Operating—coming soon
2Conventional HydroelectricHY135135Apr 1970Operating—coming soon
3Conventional HydroelectricHY135135Jan 1971Operating (Out of service, expected back within the year)—coming soon
4Conventional HydroelectricHY135135Feb 1978Operating—coming soon
5Conventional HydroelectricHY135135Jun 1978Operating (Out of service, expected back within the year)—coming soon
6Conventional HydroelectricHY135135Jun 1978Operating—coming soon

Owner / operator

Operator: USACE Northwestern Division. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
USACE Northwestern Division100.0%810 MW

Nearby plants

Within 80 km.
Lower Snake River Wind Energy Project343 MW17.1 km
Lower Snake Solar Generation BESS—17.8 km
Tucannon River Wind Farm267 MW18.1 km
Hopkins Ridge Wind157 MW23.4 km
Marengo Wind Plant234 MW30.1 km
Lower Monumental810 MW39.2 km