← Back to map

Dunlap TP 1

Guadalupe County, Texas · EIA plant ID 3582 · Operator: Guadalupe Blanco River Authority
HydroConventional HydroelectricERCOTBA: ERCO
Nameplate4MWSummer 4 MW
Generators2in service
Net generation4GWh12 mo to Dec 2025
Capacity factor12%hydro units, summer MW
Heat rate—thermal plants only
First online1927

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
024GWh200120032005200720092011201320152017201920232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%25%50%75%2005201020152020202511.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200124.377.0%—
200221.467.9%—
200319.361.1%—
200423.273.3%—
200521.467.8%—
20068.727.6%—
200723.273.5%—
200811.737.1%—
20098.426.7%—
20102063.4%—
20116.520.5%—
201200.0%—
20135.718.0%—
20143.110.0%—
201515.348.5%—
201617.354.8%—
201716.251.3%—
201812.339.0%—
2019618.9%—
202000.0%—
20230.72.2%—
20244.414.0%—
20253.711.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY1.81.8Jan 1927Operating—coming soon
2Conventional HydroelectricHY1.81.8Jan 1927Operating—coming soon

Owner / operator

Operator: Guadalupe Blanco River Authority. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Guadalupe Blanco River Authority100.0%4 MW

Nearby plants

Within 80 km.
Abbott TP 33 MW5.2 km
Niagara Bottling - Seguin5 MW8.7 km
Rio Nogales Power Project1,108 MW8.8 km
Guadalupe Generating Station1,088 MW9.4 km
Mesquite Creek LFGTE Project3 MW11 km
TP 42 MW11.2 km