Abbott TP 3Out of service

Guadalupe County, Texas · EIA plant ID 3581 · Operator: Guadalupe Blanco River Authority
HydroConventional HydroelectricERCOTBA: ERCO
Nameplate3MWSummer 3 MW
Generators2in service
Net generation0GWh12 mo to Dec 2025
Capacity factor0%hydro units, summer MW
Heat rate—thermal plants only
First online1927

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0123GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%200520102015202020250.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200115.764.0%—
200213.655.4%—
200313.153.5%—
200416.165.4%—
200514.659.5%—
20066.124.7%—
200715.864.3%—
20088.434.1%—
20095.421.9%—
201013.254.0%—
20114.819.6%—
20125.522.4%—
2013416.3%—
20142.811.3%—
201510.241.7%—
201613.655.4%—
201711.647.3%—
20189.237.6%—
201912.450.4%—
20206.225.3%—
20217.329.7%—
20225.823.5%—
20230.83.1%—
202400.0%—
202500.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY1.41.4Jan 1927Operating (Out of service)—coming soon
2Conventional HydroelectricHY1.41.4Jan 1927Operating (Out of service)—coming soon

Owner / operator

Operator: Guadalupe Blanco River Authority. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Guadalupe Blanco River Authority100.0%3 MW

Nearby plants

Within 80 km.
Dunlap TP 14 MW5.2 km
Niagara Bottling - Seguin5 MW6.2 km
TP 42 MW6.5 km
Rio Nogales Power Project1,108 MW6.5 km
Guadalupe Generating Station1,088 MW10.3 km
Nolte2 MW12.2 km