← Back to map

Merced Falls

Merced County, California · EIA plant ID 258 · Operator: Merced Irrigation District
HydroConventional HydroelectricCAISOBA: CISO
Nameplate3MWSummer 4 MW
Generators1in service
Net generation8GWh12 mo to Dec 2025
Capacity factor27%hydro units, summer MW
Heat rate—thermal plants only
First online1930

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-0.500.511.52GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%2005201020152020202527.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20011239.3%—
200210.835.1%—
200311.336.9%—
200411.537.4%—
200514.146.0%—
200614.346.8%—
200711.437.1%—
20088.929.0%—
200910.935.5%—
201012.540.7%—
201116.754.5%—
201210.233.3%—
20137.123.3%—
20144.314.1%—
2015-0.1-0.3%—
2016826.0%—
201713.243.0%—
20189.731.6%—
201912.540.8%—
20207.123.2%—
20216.320.7%—
20226.420.8%—
202311.738.1%—
20249.430.4%—
20258.427.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY3.43.5Jul 1930Operating—coming soon

Owner / operator

Operator: Merced Irrigation District. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Merced Irrigation District100.0%3 MW

Nearby plants

Within 80 km.
McSwain9 MW1.8 km
Exchequer95 MW8.7 km
Parker3 MW11.3 km
Upper Dawson4 MW18.9 km
La Grange5 MW19.1 km
UC Merced Solar Hybrid5 MW19.7 km