← Back to map

Murray

Pulaski County, Arkansas · EIA plant ID 7166 · Operator: City of North Little Rock - (AR)
HydroConventional HydroelectricMISOBA: MISO
Nameplate45MWSummer 42 MW
Generators2in service
Net generation116GWh12 mo to Dec 2025
Capacity factor31%hydro units, summer MW
Heat rate—thermal plants only
First online1988

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-505101520GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%2005201020152020202531.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2001105.128.3%—
200200.0%—
20030.20.1%—
2004148.639.9%—
200588.723.9%—
200684.422.7%—
2007148.139.9%—
2008140.537.7%—
200916544.4%—
2010137.437.0%—
201195.725.8%—
201296.325.9%—
2013134.336.2%—
2014135.436.4%—
2015108.829.3%—
2016147.939.7%—
2017108.529.2%—
201839.910.7%—
201989.624.1%—
2020159.342.8%—
2021100.527.1%—
202272.719.6%—
2023142.438.3%—
2024113.530.5%—
2025116.431.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY22.721.2Oct 1988Operating—coming soon
2Conventional HydroelectricHY22.721.2Oct 1988Operating—coming soon

Owner / operator

Operator: City of North Little Rock - (AR). Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
City of North Little Rock - (AR)100.0%45 MW

Nearby plants

Within 80 km.
Southside SD1 MW16.6 km
City of Little Rock Solar Array—17 km
Zeuber5 MW17.1 km
NLRED 2MW2 MW17.1 km
NLRED 5MW5 MW17.2 km
Two Pine Landfill Gas Recovery5 MW18.7 km