← Back to map

Bigler - PA 0436 (Flango 2)Under construction

Clearfield County, Pennsylvania · EIA plant ID 70076 · Operator: CVE US PA Bigler 436 LLC
SolarPJMBA: PJM

3 MW under construction (Solar Photovoltaic), first expected Feb 2028 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 3 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
436Solar PhotovoltaicPV33planned Feb 2028Under construction—coming soon

Owner / operator

Operator: CVE US PA Bigler 436 LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Bigler - PA 0438 (Flango 4)—0 km
Bigler - PA 0437 (Flango 3)—0 km
Bigler - PA 0409 (Flango 1)—0 km
Green Acres PA20 MW1.9 km
Sandy Ridge Wind Farm50 MW14.1 km
Sandy Ridge Wind 2, LLC88 MW18.1 km