← Back to map

Keene Branch SolarUnder construction

Hillsborough County, Florida · EIA plant ID 69461 · Operator: Tampa Electric Co
SolarBA: TEC

75 MW under construction (Solar Photovoltaic), first expected Dec 2026 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 75 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV74.574.5planned Dec 2026Under construction—coming soon

Owner / operator

Operator: Tampa Electric Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Cottonmouth Ranch Solar75 MW2.4 km
Bullfrog Creek Solar75 MW3 km
Wimauma Solar and Battery Storage115 MW4.6 km
Elder Branch75 MW7 km
Three Creeks75 MW8.8 km
Manatee2,951 MW9.8 km