← Back to map

Project Lynx

Nueces County, Texas · EIA plant ID 69286 · Operator: Project Lynx - Giga Texas Energy
BatteryBatteriesERCOTBA: ERCO
Nameplate125MWSummer 125 MW
Generators1in service
Net generation-1GWh12 mo to Aug 2026
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online2026

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-600-400-2000MWh

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
LYNXBatteriesBA125125Aug 2026Operating—coming soon

Owner / operator

Operator: Project Lynx - Giga Texas Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Project Lynx - Giga Texas Energy100.0%125 MW

Nearby plants

Within 80 km.
Sunscape Renewable Energy—12 km
Corpus Christi41 MW16.3 km
Patriot Wind Farm226 MW16.6 km
Regis Hearn10 MW18 km
Ticona Polymers Inc44 MW19.8 km
Noria Hondo Solar (Hybrid)—20.4 km