← Back to map

Singing Grass WindUnder construction

Kit Carson County, Colorado · EIA plant ID 68982 · Operator: Public Service Co of Colorado
WindBA: PSCO

603 MW under construction (Onshore Wind Turbine), first expected Sep 2027 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 603 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SGG01Onshore Wind TurbineWT603600planned Sep 2027Under construction—coming soon

Owner / operator

Operator: Public Service Co of Colorado. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Bronco Plains Wind II, LLC200 MW9.9 km
Crossing Trails Wind Power Project LLC.104 MW17.4 km
Bronco Plains Wind, LLC300 MW19.1 km
Dusty Rose Wind502 MW28.4 km
Dry Land Prairie Energy Storage—38.5 km
Kit Carson Windpower51 MW46 km