← Back to map

Quantum BESSUnder construction

Haskell County, Texas · EIA plant ID 68759 · Operator: Intersect USA, LLC
BatteryERCOTBA: ERCO

422 MW under construction (Batteries), first expected Nov 2026 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 422 MW building
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
IPQ1BBatteriesBA422.4323.6planned Nov 2026Under construction—coming soon

Owner / operator

Operator: Intersect USA, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Quantum Solar—0.1 km
OCI Alamo 7 LLC100 MW3.2 km
Azure Sky Solar316 MW5.2 km
Quantum II BESS—13.7 km
Quantum II Solar—14 km
Briggs Solar, LLC—14.7 km