Walleye Solar (Sandow II)Planned

Milam County, Texas · EIA plant ID 68231 · Operator: EDF Renewable Asset Holdings, Inc.
SolarERCOTBA: ERCO

369 MW planned (Solar Photovoltaic), first expected Dec 2026 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SDTWOSolar PhotovoltaicPV369369planned Dec 2026Planned—coming soon

Owner / operator

Operator: EDF Renewable Asset Holdings, Inc.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Stoneridge Solar, LLC200 MW2.4 km
Gransolar Texas One, LLC50 MW7.4 km
Adelite Storage Project LLC—13.3 km
Sandow Lakes Energy Station—19.5 km
TX21 River Valley Storage 250 MW31 km
TX19 River Valley Storage 150 MW31.2 km