Purple Sage Energy CenterPlanned

Clark County, Nevada · EIA plant ID 68209 · Operator: Noble Solar LLC
BatteryCAISOBA: CISO

800 MW planned (Batteries, Solar Photovoltaic), first expected Nov 2028 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service
Net generation—GWh12 mo
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PSGBSBatteriesBA400400planned Nov 2028Planned—coming soon
PSGPVSolar PhotovoltaicPV400400planned Nov 2028Planned—coming soon

Owner / operator

Operator: Noble Solar LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Yellow Pine Solar190 MW5 km
Yellow Pine II210 MW5.3 km
Rough Hat—8.2 km
MDU / NVSS-II14 MW31.1 km
Goodsprings Waste Heat Recovery8 MW43.1 km
IKEA Las Vegas 4621 MW47.4 km