← Back to map

LPEA Sunnyside Solar 1 Facility

La Plata County, Colorado · EIA plant ID 67952 · Operator: la plata electric assn inc
SolarSolar PhotovoltaicBA: WACM
Nameplate2MWSummer 2 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor30%solar units, summer MW
Heat rate—thermal plants only
First online2024

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400MWh20242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%60%20242025202629.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20244.661.1%—
20254.429.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PV001Solar PhotovoltaicPV1.71.7Jul 2024Operating—coming soon

Owner / operator

Operator: la plata electric assn inc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
la plata electric assn inc100.0%2 MW

Nearby plants

Within 80 km.
Williams Ignacio Natural Gas Plant6 MW7.1 km
Vallecito Hydroelectric6 MW37.6 km
Navajo Dam30 MW41.6 km
Tacoma5 MW45 km
Foxtail Flats Solar, LLC—46.7 km
Four Mile Mesa Solar, LLC—46.7 km