Nameplate3MWSummer 3 MW
Generators2in service
Net generation5GWh12 mo to Dec 2025
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2024
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2024 | 5.6 | 20.0% | — |
| 2025 | 5.3 | 18.8% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| PV-A | Solar Photovoltaic | PV | 1.6 | 1.6 | Jan 2024 | Operating | — | coming soon |
| PV-B | Solar Photovoltaic | PV | 1.6 | 1.6 | Jan 2024 | Operating | — | coming soon |
Owner / operator
Operator: AstraZeneca Pharmaceuticals. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| AstraZeneca Pharmaceuticals | 100.0% | 3 MW |
Nearby plants
Within 80 km.
| Brookside Newark | 3 MW | 2.4 km |
| Red Lion Energy Center | 25 MW | 7.8 km |
| MD - WL Gore - Appleton | 1 MW | 8.5 km |
| Delaware City 10 | 19 MW | 8.6 km |
| Cecil County CCVT HS | 2 MW | 8.8 km |
| Delaware City Plant | 324 MW | 9.2 km |