Columbia County, Florida · EIA plant ID 67206 · Operator: FRP Columbia County Solar, LLC
SolarSolar PhotovoltaicBA: FPC
Nameplate75MWSummer 75 MW
Generators1in service
Net generation155GWh12 mo to Aug 2026
Capacity factor24%solar units, summer MW
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
05101520GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%202420252026202723.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202438.535.3%—
2025194.729.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
COLSSolar PhotovoltaicPV74.574.5Nov 2024Operating—coming soon

Owner / operator

Operator: FRP Columbia County Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
FRP Columbia County Solar, LLC100.0%75 MW

Nearby plants

Within 80 km.
Columbia Solar Power Plant75 MW3.7 km
County Line Renewable Energy Center75 MW9.6 km
High Springs Solar Power Plant75 MW12.2 km
Hildreth Solar Power Plant75 MW12.5 km
Bell Ridge Solar75 MW18.3 km
Trenton Solar Power Plant75 MW29.4 km