← Back to map

Copperhead Solar, LLC

McLennan County, Texas · EIA plant ID 67019 · Operator: Geronimo Energy
SolarBatteriesSolar PhotovoltaicERCOTBA: ERCO
Nameplate250MWSummer 250 MW
Generators2in service
Net generation263GWh12 mo to Aug 2026
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0102030GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202420252026202720.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202494.621.9%—
2025296.722.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CHSLRSolar PhotovoltaicPV150150Sep 2024Operating—coming soon
CHSTGBatteriesBA100100Sep 2024Operating—coming soon

Owner / operator

Operator: Geronimo Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Geronimo Energy100.0%250 MW

Nearby plants

Within 80 km.
Roseland Solar Project, LLC52 MW3.6 km
True North Solar, LLC239 MW6.6 km
Sandy Creek Energy Station1,008 MW9.6 km
Prairie Hill Wind Project300 MW11.9 km
Marlin Solar5 MW18.2 km
Naduah Solar—19.4 km