Midpoint Solar, LLC
Hill County, Texas · EIA plant ID 66897 · Operator: Sunraycer Assets I LLC
Nameplate148MWSummer 148 MW
Generators2in service
Net generation98GWh12 mo to Aug 2026
Capacity factor23%solar units, summer MW
Heat rate—thermal plants only
First online2026
The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| MIDBA | Batteries | BA | 50 | 50 | Jun 2026 | Operating | — | coming soon |
| MIDPV | Solar Photovoltaic | PV | 97.5 | 97.5 | Mar 2026 | Operating | — | coming soon |
Owner / operator
Operator: Sunraycer Assets I LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Sunraycer Assets I LLC | 100.0% | 148 MW |
Nearby plants
Within 80 km.
| TPE Whitney Solar, LLC | 10 MW | 7.4 km |
| Three W Solar | 111 MW | 15.3 km |
| Hillsboro Solar Project | — | 21 km |
| Edens Solar | — | 22.7 km |
| Hill Solar II | — | 26 km |
| BPL Files Solar | 158 MW | 26.7 km |