Orion I Solar Project

Milam County, Texas · EIA plant ID 66859 · Operator: Ben Milam Solar 1 LLC
SolarSolar PhotovoltaicERCOTBA: ERCO
Nameplate200MWSummer 200 MW
Generators1in service
Net generation445GWh12 mo to Aug 2026
Capacity factor25%solar units, summer MW
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02040GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%202420252026202725.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2024193.426.3%—
2025446.125.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ORN1Solar PhotovoltaicPV200200Aug 2024Operating—coming soon

Owner / operator

Operator: Ben Milam Solar 1 LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Ben Milam Solar 1 LLC100.0%200 MW

Nearby plants

Within 80 km.
Orion II Solar Project250 MW7.3 km
BT Jungmann40 MW11.6 km
Orion III Solar Project250 MW12.4 km
Hermes Storage BESS—13.6 km
Hermes Solar PV—14.2 km