Sacramento Valley Energy Center, LLCUnder construction

Sacramento County, California · EIA plant ID 65808 · Operator: Sacramento Valley Energy Center, LLC
SolarBA: BANC

300 MW under construction (Batteries, Solar Photovoltaic), first expected Dec 2029 · EIA-860M

Nameplate—MWSummer — MW
Generators0in service · 300 MW building
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—thermal plants only
First online—

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BSVECBatteriesBA100100planned Dec 2029Under construction—coming soon
SVECSolar PhotovoltaicPV200200planned Dec 2029Under construction—coming soon

Owner / operator

Operator: Sacramento Valley Energy Center, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).

Nearby plants

Within 80 km.
Juniper Creek Storage—2.7 km
Aerojet II2 MW4.3 km
Aerojet I3 MW5 km
Kiefer Landfill Generating Phase II6 MW6.4 km
FAA NorCal TRACON1 MW6.5 km
Kiefer Landfill15 MW6.5 km