← Back to map

Aerojet I

Sacramento County, California · EIA plant ID 57697 · Operator: Altus Power America Management, LLC
SolarSolar PhotovoltaicCAISOBA: BANC
Nameplate3MWSummer 3 MW
Generators1in service
Net generation6GWh12 mo to Dec 2025
Capacity factor23%solar units, summer MW
Heat rate—thermal plants only
First online2009

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh201120122013201420152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2012201420162018202020222024202622.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20116.524.8%—
20126.826.0%—
20137.127.1%—
20146.424.3%—
20156.424.2%—
20165.721.7%—
20175.119.5%—
2018519.1%—
20195.922.5%—
20205.721.7%—
20215.922.5%—
20225.922.5%—
20235.922.4%—
20245.119.5%—
2025622.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Solar PhotovoltaicPV33Dec 2009Operating—coming soon

Owner / operator

Operator: Altus Power America Management, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Altus Power America Management, LLC100.0%3 MW

Nearby plants

Within 80 km.
Aerojet II2 MW0.8 km
Intel Folsom Phase 21 MW3.3 km
Intel Folsom Phase 35 MW3.6 km
Intel Folsom1 MW3.6 km
Sacramento Valley Energy Center, LLC—5 km
Nimbus13 MW5.6 km