← Back to map

Deerfield Wind Energy 2

Huron County, Michigan · EIA plant ID 65742 · Operator: Deerfield Wind Energy 2, LLC
WindOnshore Wind TurbineMISOBA: MISO
Nameplate112MWSummer 112 MW
Generators1in service
Net generation279GWh12 mo to Aug 2026
Capacity factor28%wind units, summer MW
Heat rate—thermal plants only
First online2023

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
010203040GWh202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2023202420252026202728.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2023181.422.0%—
202430931.4%—
2025299.830.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
DWF02Onshore Wind TurbineWT112.1112.1Mar 2023Operating—vestas V162-5.6

Owner / operator

Operator: Deerfield Wind Energy 2, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Deerfield Wind Energy 2, LLC100.0%112 MW

Nearby plants

Within 80 km.
Deerfield Wind Energy, LLC149 MW2.5 km
Big Turtle Wind Farm 229 MW6.4 km
Sigel Wind Park64 MW11.3 km
Big Turtle Wind Farm, LLC20 MW11.3 km
Silver Creek Solar Park—17.7 km
Ubly12 MW23.6 km