← Back to map

Big Turtle Wind Farm, LLC

Huron County, Michigan · EIA plant ID 58891 · Operator: DTE Sustainable Generation
WindOnshore Wind TurbineMISOBA: MISO
Nameplate20MWSummer 20 MW
Generators1in service
Net generation76GWh12 mo to Dec 2025
Capacity factor17%wind units, summer MW
Heat rate—thermal plants only
First online2014

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
05101520GWh20152016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), wind units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%201420162018202020222024202617.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20143.322.2%—
201576.943.9%—
201679.433.0%—
2017186.943.2%—
2018181.241.9%—
201971.516.5%—
202066.515.3%—
202157.432.8%—
202261.735.2%—
202366.137.7%—
202469.939.8%—
202575.643.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BTWF1Onshore Wind TurbineWT2020Dec 2014Operating—gamesa G114-2.0
BTWF2Onshore Wind TurbineWT29.429.4Oct 2016not_current—gamesa G114-2.0

Owner / operator

Operator: DTE Sustainable Generation. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
DTE Sustainable Generation100.0%20 MW

Nearby plants

Within 80 km.
Sigel Wind Park64 MW0.1 km
Big Turtle Wind Farm 229 MW7.7 km
Deerfield Wind Energy 2112 MW11.3 km
Deerfield Wind Energy, LLC149 MW13.8 km
Ubly12 MW19.1 km
Minden Wind Park32 MW20.2 km