← Back to map

Millville Hydro Station

Jefferson County, West Virginia · EIA plant ID 6546 · Operator: Eagle Creek RE LLC
HydroConventional HydroelectricPJMBA: PJM
Nameplate3MWSummer 2 MW
Generators3in service
Net generation8GWh12 mo to Dec 2025
Capacity factor37%hydro units, summer MW
Heat rate—thermal plants only
First online1913

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.511.5GWh200220042006200820102012201420162018202020222024

Capacity factor by year

Net MWh ÷ (summer MW × hours), hydro units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%100%200%2005201020152020202536.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200200.0%—
200318.2260.3%—
200416.879.7%—
200510.449.6%—
200610.349.2%—
20071047.6%—
2008942.5%—
20098.138.6%—
20108.339.3%—
201111.253.2%—
201211.755.6%—
201310.550.0%—
20142.210.5%—
201511.956.7%—
201611.755.7%—
20178.540.6%—
201812.459.0%—
201910.349.2%—
20201152.2%—
202110.349.2%—
20227.334.6%—
20236.631.4%—
20248.640.9%—
20257.736.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1Conventional HydroelectricHY0.80.6Jan 1913Operating—coming soon
2Conventional HydroelectricHY10.8Dec 1939Operating—coming soon
3Conventional HydroelectricHY11Dec 1938Operating—coming soon

Owner / operator

Operator: Eagle Creek RE LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
PE Hydro Generation, LLC100.0%3 MW

Nearby plants

Within 80 km.
Blake Solar Plant96 MW4.3 km
Rippon Energy Facility—10.6 km
Dam No. 4 Hydro Station2 MW24.7 km
Redbud Run Solar—26.7 km
Dickersonretired28.4 km
Dickerson326 MW28.4 km