San Bernardino County, California · EIA plant ID 65456 · Operator: Southern California Edison Co
BatteryBatteriesCAISOBA: CISO
Nameplate113MWSummer 113 MW
Generators1in service
Net generation-29GWh12 mo to Aug 2026
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online2024

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
-3-2-10GWh20252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20240——
2025-19——

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SEPARBatteriesBA112.5112.5Aug 2024Operating—coming soon

Owner / operator

Operator: Southern California Edison Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Southern California Edison Co100.0%113 MW

Nearby plants

Within 80 km.
Grapeland Hybrid60 MW0.2 km
Foundation IE1 MW0.9 km
SunE Rochester1 MW1.2 km
VS BI 4th St. RCMU LLC—1.3 km
Etiwanda24 MW1.5 km