← Back to map

Chambers 4 - Eastvale LGB3

Riverside County, California · EIA plant ID 65238 · Operator: GSRP
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation5GWh12 mo to Dec 2025
Capacity factor22%solar units, summer MW
Heat rate—thermal plants only
First online2019

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400MWh20212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20212022202320242025202621.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20212.913.9%—
202200.0%—
20233.818.0%—
20243.918.7%—
20254.521.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Solar PhotovoltaicPV2.42.4Feb 2019Operating—coming soon

Owner / operator

Operator: GSRP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
GRE Fund 4 LGB3 LLC100.0%2 MW

Nearby plants

Within 80 km.
Chambers 4 - Eastvale DCA22 MW0.6 km
Mira Loma Peaker50 MW1 km
Mira Loma Energy Storage Facility20 MW1.1 km
Roadhouse Energy Center—1.8 km
Mira Loma3 MW2.2 km
Solar Photovoltaic Project #33retired4.1 km