Altice - Hicksville
Nassau County, New York · EIA plant ID 65212 · Operator: Bloom Energy
Nameplate2MWSummer 2 MW
Generators1in service
Net generation15GWh12 mo to Dec 2025
Capacity factor87%gas/coal/oil units, summer MW
Heat rate8,469Btu/kWhfossil units, electric fuel, HHV
First online2021Runs as baseload
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), gas/coal/oil units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2021 | 4.9 | 66.5% | 6,402 |
| 2022 | 17.5 | 99.7% | 6,628 |
| 2023 | 16.9 | 96.6% | 6,706 |
| 2024 | 16 | 91.0% | 7,110 |
| 2025 | 15.3 | 87.2% | 8,469 |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| ATC04 | Other Natural Gas | FC | 2 | 2 | Aug 2021 | Operating | — | coming soon |
Owner / operator
Operator: Bloom Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Bloom Energy | 100.0% | 2 MW |
Nearby plants
Within 80 km.
| Bloom-Altice Fuel Cell | 2 MW | 0.8 km |
| Bethpage Power Plant | 240 MW | 1.5 km |
| SUNY Old Westbury College | retired | 6.7 km |
| Covanta Hempstead | 79 MW | 7.6 km |
| Nassau Energy Corp | retired | 8.1 km |
| Pinelawn Power LLC | 82 MW | 10.1 km |