SulusSolar25

Marion County, Oregon · EIA plant ID 64034 · Operator: Enerparc Inc.
SolarSolar PhotovoltaicBA: PGE
Nameplate2MWSummer 2 MW
Generators1in service
Net generation3GWh12 mo to Dec 2025
Capacity factor17%solar units, summer MW
Heat rate—thermal plants only
First online2020

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300400MWh20212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%202020212022202320242025202617.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20200.24.3%—
20213.317.0%—
20223.417.4%—
20233.417.6%—
20243.317.0%—
20253.317.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SS25Solar PhotovoltaicPV2.22.2Oct 2020Operating—coming soon

Owner / operator

Operator: Enerparc Inc.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Enerparc Inc.100.0%2 MW

Nearby plants

Within 80 km.
SSD Marion 6, LLC2 MW2.1 km
Baldock Solar Highway1 MW3.8 km
Coffee Creek BESS17 MW8.5 km
Case Creek Solar2 MW13.1 km
OR - Solops - SPI 18 - Dover2 MW13.2 km
BristolSolar3 MW13.5 km