← Back to map

Amaterasu LLC

Worcester County, Massachusetts · EIA plant ID 64000 · Operator: AES Distributed Energy
SolarBatteriesSolar PhotovoltaicISONEBA: ISNE
Nameplate8MWSummer 8 MW
Generators2in service
Net generation7GWh12 mo to Dec 2025
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2021

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh2022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%20212022202320242025202617.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20212.29.3%—
20224.110.6%—
20237.117.8%—
20246.817.0%—
2025717.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BESSBatteriesBA3.23.2Jun 2021Operating—coming soon
DRCSolar PhotovoltaicPV4.64.6Jun 2021Operating—coming soon

Owner / operator

Operator: AES Distributed Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
AES Distributed Energy100.0%8 MW

Nearby plants

Within 80 km.
ZPD-PT Solar Project 2017-038 Hybrid LLC9 MW0.4 km
EDF Lancaster5 MW1.3 km
Nationwide4 MW2.3 km
Shirley Landfill1 MW2.5 km
Brockelman Road Solar 23 MW5 km
Wachusett Solar2 MW5 km