← Back to map

Lick Creek Solar, LLC

Stokes County, North Carolina · EIA plant ID 63811 · Operator: SunStrong Management
SolarSolar PhotovoltaicBA: DUK
Nameplate50MWSummer 50 MW
Generators1in service
Net generation105GWh12 mo to Aug 2026
Capacity factor24%solar units, summer MW
Heat rate—thermal plants only
First online2022

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0510GWh2023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20222023202420252026202724.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202283.322.7%—
2023110.625.3%—
2024108.624.7%—
2025109.525.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PGR27Solar PhotovoltaicPV5050Mar 2022Operating—coming soon

Owner / operator

Operator: SunStrong Management. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
SunStrong Management100.0%50 MW

Nearby plants

Within 80 km.
Carol Jean Solar4 MW4 km
Belews Creek2,491 MW6.1 km
Bear Branch Solar—6.4 km
Salem Energy Systems LLC5 MW11.3 km
Germantown Solar, LLC2 MW12 km
Waste Management Piedmont LFGTE Project2 MW12.7 km