SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate30MWSummer 30 MW
Generators1in service
Net generation63GWh12 mo to Aug 2026
Capacity factor24%solar units, summer MW
Heat rate—thermal plants only
First online2020

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02468GWh202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2020202120222023202420252026202723.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20205628.3%—
20217528.5%—
202274.428.3%—
202368.926.2%—
202464.924.6%—
202565.825.0%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GEN1Solar PhotovoltaicPV3030Apr 2020Operating—coming soon

Owner / operator

Operator: GSRP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
GSRP100.0%30 MW

Nearby plants

Within 80 km.
Nickel 1 Solar Facility2 MW3.9 km
Lost Hills Cogeneration Plant7 MW8.6 km
Flying Goose3 MW10 km
Wildwood Solar I, LLC20 MW10.1 km
Wonderful Huller & Shellling2 MW10.2 km