← Back to map

Cottonwood Solar, LLC

Northampton County, North Carolina · EIA plant ID 63293 · Operator: Alchemy Renewable Energy
SolarSolar PhotovoltaicPJMBA: PJM
Nameplate3MWSummer 3 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor17%solar units, summer MW
Heat rate—thermal plants only
First online2018

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400600MWh2019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2019202020212022202320242025202616.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20195.922.3%—
20205.219.9%—
20215.219.8%—
20225.219.6%—
20234.517.2%—
20244.617.6%—
20254.316.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
NCCWDSolar PhotovoltaicPV33Jan 2018Operating—coming soon

Owner / operator

Operator: Alchemy Renewable Energy. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Alchemy Renewable Energy100.0%3 MW

Nearby plants

Within 80 km.
510 REPP One1 MW1.4 km
Gaston Solar5 MW3.8 km
KapStone Kraft Paper Corp28 MW4.2 km
Long Farm 46 Solar, LLC5 MW4.6 km
Hemlock Solar5 MW4.6 km
Garysburg Solar5 MW4.9 km