← Back to map

Plainfield Solar 2

Windham County, Connecticut · EIA plant ID 63263 · Operator: Ecos Energy LLC
SolarSolar PhotovoltaicISONEBA: ISNE
Nameplate1MWSummer 1 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor17%solar units, summer MW
Heat rate—thermal plants only
First online2020

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150MWh20212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%202020212022202320242025202617.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20200.68.7%—
20211.415.6%—
20221.517.4%—
20231.516.8%—
20241.516.9%—
20251.517.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PLFD2Solar PhotovoltaicPV11Apr 2020Operating—coming soon

Owner / operator

Operator: Ecos Energy LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Ecos Energy LLC100.0%1 MW

Nearby plants

Within 80 km.
Plainfield Solar 11 MW0.4 km
Plainfield Renewable Energy LLC43 MW2.3 km
Plainfield Solar One—4.9 km
Exeter Energy LP—7.8 km
Quinebaug Solar49 MW8.2 km
Wyre Wynd Hydroelectric Project3 MW10.3 km