Nameplate460MWSummer 460 MW
Generators2in service
Net generation1,025GWh12 mo to Aug 2026
Capacity factor28%solar units, summer MW
Heat rate—thermal plants only
First online2021

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0255075100GWh20222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%20%40%202120222023202420252026202727.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2021597.638.8%—
2022939.925.6%—
2023905.324.7%—
2024908.424.7%—
20251,005.327.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
2WPBABatteriesBA4040Oct 2021Operating—coming soon
2WPSOSolar PhotovoltaicPV420420Aug 2021Operating—coming soon

Owner / operator

Operator: 2W Permian Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
2W Permian Solar, LLC100.0%460 MW

Nearby plants

Within 80 km.
Ector County Energy Center359 MW7.5 km
Oxy Renewable Energy - Goldsmith17 MW16.3 km
Goldsmith9 MW18.6 km
Bakke9 MW20 km
N. Mary Francis9 MW23.5 km
Tumbleweed9 MW26.3 km