← Back to map

Caden Energix Hickory LLC

Chesapeake City County, Virginia · EIA plant ID 63084 · Operator: Caden Energix Hickory LLC
SolarSolar PhotovoltaicPJMBA: PJM
Nameplate32MWSummer 32 MW
Generators2in service
Net generation53GWh12 mo to Aug 2026
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2020

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
02468GWh202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2020202120222023202420252026202718.8% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
202014.813.6%—
202164.723.1%—
202256.320.1%—
202351.818.5%—
202457.720.5%—
202557.120.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
ENX02Solar PhotovoltaicPV2020Aug 2020Operating—coming soon
ENX03Solar PhotovoltaicPV1212Sep 2020Operating—coming soon

Owner / operator

Operator: Caden Energix Hickory LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Caden Energix Hickory LLC100.0%32 MW

Nearby plants

Within 80 km.
Bedford Solar70 MW8.8 km
Chesapeake Solar Project132 MW11.4 km
Oak Trail Solar, LLC100 MW13.3 km
Grassfield Solar20 MW14.2 km
Summit Farms Solar62 MW17.2 km
Ranchland Solar, LLC60 MW17.2 km