Hertford Solar Power, LLCRetirement planned
Hertford County, North Carolina · EIA plant ID 63024 · Operator: Four Brothers 2, LLC
Nameplate10MWSummer 10 MW
Generators1in service
Net generation21GWh12 mo to Dec 2025
Capacity factor24%solar units, summer MW
Heat rate—thermal plants only
First online2022Retirement planned Jan 2061
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2022 | 6.4 | 12.5% | — |
| 2023 | 20.7 | 23.7% | — |
| 2024 | 18.7 | 21.3% | — |
| 2025 | 20.7 | 23.7% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| KEH | Solar Photovoltaic | PV | 10 | 10 | Jun 2022 | Operating · retirement planned | Jan 2061 | coming soon |
Owner / operator
Operator: Four Brothers 2, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Four Brothers 2, LLC | 100.0% | 10 MW |
Nearby plants
Within 80 km.
| Baker PV 1 | 5 MW | 2.9 km |
| Aulander Holloman Solar, LLC | 99 MW | 4.3 km |
| Bradley PV1 | 5 MW | 4.4 km |
| Simons Farm | 5 MW | 5.1 km |
| Ahoskie | 5 MW | 5.3 km |
| Aulander Hwy 42 Solar, LLC | 5 MW | 5.6 km |