Cooke County, Texas · EIA plant ID 62773 · Operator: Enerparc Inc.
SolarSolar PhotovoltaicERCOTBA: ERCO
Nameplate59MWSummer 59 MW
Generators1in service
Net generation114GWh12 mo to Aug 2026
Capacity factor22%solar units, summer MW
Heat rate—thermal plants only
First online2020

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2020202120222023202420252026202722.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20205.813.3%—
2021131.925.5%—
202214227.5%—
2023127.824.7%—
2024125.124.1%—
2025122.523.7%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
BTCOOSolar PhotovoltaicPV5959Dec 2020Operating—coming soon

Owner / operator

Operator: Enerparc Inc.. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Enerparc Inc.100.0%59 MW

Nearby plants

Within 80 km.
North Gainesville Solar5 MW12.2 km
Wildcat Creek Wind Farm LLC175 MW13.9 km
Compadre Solar150 MW14.4 km
Oakley BESS—14.6 km
Regis Muenster10 MW17.4 km
Tyler Bluff Wind Project, LLC126 MW24.7 km