← Back to map

Solar Star Palo Alto I, LLC

Santa Clara County, California · EIA plant ID 62732 · Operator: DG 1 Acquisition Co., LLC
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate1MWSummer 1 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2019

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200MWh202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%5%10%15%2019202020212022202320242025202617.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20190.613.0%—
20202.219.1%—
20212.219.1%—
20222.118.8%—
20232.118.6%—
2024217.6%—
2025217.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
SSPAISolar PhotovoltaicPV1.31.3Aug 2019Operating—coming soon

Owner / operator

Operator: DG 1 Acquisition Co., LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
DG 1 Acquisition Co., LLC100.0%1 MW

Nearby plants

Within 80 km.
Stanford Campus Solar4 MW2.8 km
City of Palo Altoretired4.6 km
SRI International Cogen Project6 MW5.4 km
Equinix Caspian Dr. Fuel Cell5 MW8.6 km
AT&T - Redwood City1 MW9 km
Lockheed Martin Sunnyvaleretired10.7 km