← Back to map

Palmetto Plains

Orangeburg County, South Carolina · EIA plant ID 62679 · Operator: Cubico USA, LLC
SolarSolar PhotovoltaicBA: SCEG
Nameplate75MWSummer 75 MW
Generators1in service
Net generation126GWh12 mo to Aug 2026
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2019

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh2020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20192020202120222023202420252026202719.2% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20196319.0%—
2020158.124.0%—
2021160.224.4%—
2022138.821.1%—
202312919.6%—
2024118.317.9%—
2025126.119.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1405Solar PhotovoltaicPV7575Jul 2019Operating—coming soon

Owner / operator

Operator: Cubico USA, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Cubico USA, LLC100.0%75 MW

Nearby plants

Within 80 km.
TWE Bowman Solar Project75 MW3 km
Huntley75 MW5.9 km
Substation 20 Plant2 MW17.4 km
Rowesville Rd Plant10 MW17.6 km
SR Cordova—22.2 km
Bull Street Plant2 MW23.1 km