UMCES Ground Mount

Dorchester County, Maryland · EIA plant ID 62405 · Operator: Standard Solar
SolarSolar PhotovoltaicPJMBA: PJM
Nameplate2MWSummer 2 MW
Generators1in service
Net generation3GWh12 mo to Dec 2025
Capacity factor19%solar units, summer MW
Heat rate—thermal plants only
First online2018

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0100200300400MWh2019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20182019202020212022202320242025202619.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20183.622.3%—
20192.413.6%—
20202.916.6%—
20213.620.4%—
20223.620.6%—
20233.519.7%—
20243.519.6%—
20253.419.3%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
X0009Solar PhotovoltaicPV22Feb 2018Operating—coming soon

Owner / operator

Operator: Standard Solar. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Standard Solar100.0%2 MW

Nearby plants

Within 80 km.
Mustang One2 MW2.9 km
Egypt Road Solar51 MW6.5 km
CNE at Cambridge MD3 MW12.5 km
Cabin Creek MD2 MW21.1 km
MEBA2 MW21.1 km
Easton31 MW22.3 km