Moody Air Force Base Solar
Lowndes County, Georgia · EIA plant ID 62377 · Operator: Georgia Power Co
Nameplate99MWSummer 99 MW
Generators2in service
Net generation84GWh12 mo to Aug 2026
Capacity factor—not meaningful for storage
Heat rate—thermal plants only
First online2020
The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
No capacity factor available.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2020 | 53.2 | — | — |
| 2021 | 94.6 | — | — |
| 2022 | 98.8 | — | — |
| 2023 | 94 | — | — |
| 2024 | 68 | — | — |
| 2025 | 84.2 | — | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| 1 | Solar Photovoltaic | PV | 49.5 | 49.5 | Jun 2020 | Operating | — | coming soon |
| 2 | Batteries | BA | 49.5 | 49.5 | Apr 2026 | Operating | — | coming soon |
Owner / operator
Operator: Georgia Power Co. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Georgia Power Co | 100.0% | 99 MW |
Nearby plants
Within 80 km.
| Valdosta Water Treatment Plant | 3 MW | 5.6 km |
| Valdosta Prison | 1 MW | 9.7 km |
| South Georgia Medical Center | 6 MW | 12.3 km |
| Lowndes IDA | 2 MW | 13.6 km |
| Valdosta | 1 MW | 16.4 km |