Valdosta Prison

Lowndes County, Georgia · EIA plant ID 61468 · Operator: Madison Energy Holdings LLC
SolarSolar PhotovoltaicBA: SOCO
Nameplate1MWSummer 1 MW
Generators1in service
Net generation2GWh12 mo to Dec 2025
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2017

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
050100150200MWh20182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2018202020222024202618.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20170.718.6%—
20182.120.0%—
20192.119.6%—
2020219.0%—
20211.917.9%—
20221.816.9%—
20231.817.4%—
20241.716.5%—
20251.918.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GPVP1Solar PhotovoltaicPV11.2Aug 2017Operating—coming soon

Owner / operator

Operator: Madison Energy Holdings LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Madison Energy Holdings LLC100.0%1 MW

Nearby plants

Within 80 km.
South Georgia Medical Center6 MW4.3 km
Valdosta Water Treatment Plant3 MW4.7 km
Moody Air Force Base Solar99 MW9.7 km
Lowndes IDA2 MW10 km
Lowndes Cowart3 MW10.4 km
Pecan Row Landfill To Electric Facility6 MW11.2 km