← Back to map

Southwick Solar PV

Hampden County, Massachusetts · EIA plant ID 62082 · Operator: NSTAR Electric Company
SolarSolar PhotovoltaicISONEBA: ISNE
Nameplate5MWSummer 5 MW
Generators1in service
Net generation8GWh12 mo to Aug 2026
Capacity factor18%solar units, summer MW
Heat rate—thermal plants only
First online2019

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh201820192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20192020202120222023202420252026202718.0% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20180——
20197.416.9%—
20208.319.0%—
20218.419.1%—
20229.421.5%—
20238.319.0%—
20248.519.4%—
20257.917.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
REC34Solar PhotovoltaicPV55Jan 2019Operating—coming soon

Owner / operator

Operator: NSTAR Electric Company. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
NSTAR Electric Company100.0%5 MW

Nearby plants

Within 80 km.
Southwick Solar, LLC Community Solar5 MW1.9 km
Kearsarge Southwick LLC3 MW4.3 km
CES Agawam Tuckahoe Solar Hybrid6 MW5 km
Goose Pond Solar4 MW5.3 km
Route 57 Solar2 MW7.2 km
ENGIE 2019 ProjectCo-MA1, LLC5 MW8 km