← Back to map

Pacific Ethanol Madera Solar Array

Madera County, California · EIA plant ID 61989 · Operator: seaboard energy california, llc
SolarSolar PhotovoltaicCAISOBA: CISO
Nameplate4MWSummer 4 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor12%solar units, summer MW
Heat rate—thermal plants only
First online2018

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh2019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%20182019202020212022202320242025202611.7% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
2018213.8%—
20199.327.1%—
202038.9%—
202125.9%—
20221.75.0%—
20231.44.2%—
20241.64.7%—
2025411.8%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PVSolar PhotovoltaicPV4.33.9Aug 2018Operating—coming soon

Owner / operator

Operator: seaboard energy california, llc. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
seaboard energy california, llc100.0%4 MW

Nearby plants

Within 80 km.
Borden Solar Farm50 MW3 km
Madera Community Hospital1 MW7.2 km
CA - Madera USD - Madera South HS1 MW7.9 km
Sealed Air Madera Solar Project4 MW8.2 km
KDC Solar Madera LLC10 MW11.8 km
Jade Solar 3—15.6 km