← Back to map

Titan Solar

Arapahoe County, Colorado · EIA plant ID 61811 · Operator: Titan Solar, LLC
SolarSolar PhotovoltaicBA: PSCO
Nameplate50MWSummer 50 MW
Generators1in service
Net generation98GWh12 mo to Aug 2026
Capacity factor22%solar units, summer MW
Heat rate—thermal plants only
First online2018

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh20192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%2018202020222024202622.3% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20182.46.5%—
2019103.623.7%—
202010223.2%—
2021104.623.9%—
2022109.925.1%—
2023102.123.3%—
20249722.1%—
202597.422.2%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PCECSolar PhotovoltaicPV5050Dec 2018Operating—coming soon

Owner / operator

Operator: Titan Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Titan Solar, LLC100.0%50 MW

Nearby plants

Within 80 km.
Victory Solar LLC13 MW37.8 km
Canyon Peak Power Station157 MW38.1 km
Pioneer Solar (CO), LLC80 MW39 km
Hunter Solar, LLC (CO)75 MW39.2 km
Cedar Point Wind252 MW41.2 km
Oak Leaf - CSG Portfolio (OL 39)2 MW44.2 km