← Back to map

Sequoyah

Hamilton County, Tennessee · EIA plant ID 6152 · Operator: Tennessee Valley Authority
NuclearNuclearBA: TVA
Nameplate2,441MWSummer 2,278 MW
Generators2in service
Net generation17,866GWh12 mo to Aug 2026
Capacity factor90%nuclear units, summer MW
Heat rate—thermal plants only
First online1981

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
05001,0001,500GWh2001200320052007200920112013201520172019202120232025

Capacity factor by year

Net MWh ÷ (summer MW × hours), nuclear units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%50%100%2005201020152020202589.5% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
200118,949.996.6%—
200218,495.693.8%—
200315,603.878.2%—
200418,755.493.8%—
200518,999.295.3%—
200618,000.790.2%—
200718,650.793.6%—
200818,917.394.7%—
200917,754.589.0%—
201018,000.890.2%—
201118,688.293.7%—
201216,585.682.9%—
201318,52692.8%—
201418,892.494.7%—
201516,511.382.8%—
201617,242.686.2%—
201718,241.391.4%—
201817,703.788.7%—
201918,064.690.5%—
202019,099.295.5%—
202117,654.888.5%—
202218,827.394.4%—
202319,227.696.4%—
202413,427.367.1%—
202513,059.965.5%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
1NuclearST1,220.51,152Jul 1981Operating—coming soon
2NuclearST1,220.51,125.7Jun 1982Operating—coming soon

Owner / operator

Operator: Tennessee Valley Authority. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Tennessee Valley Authority100.0%2,441 MW

Nearby plants

Within 80 km.
Volkswagen Solar System8 MW14.7 km
Chickamauga160 MW18.7 km
Chattanooga Metropolitan Airport Solar3 MW24.9 km
SR Sequatchie8 MW29.8 km
Bowater Newsprint Calhoun Operationretired31.4 km
SR Marion, LLC1 MW32.2 km