BellefonteOut of service
Jackson County, Alabama · EIA plant ID 6150 · Operator: Tennessee Valley Authority
Nameplate14MWSummer 14 MW
Generators2in service
Net generation—GWh12 mo
Capacity factor—no 923 generation in the last 12 months
Heat rate—Btu/kWhfossil units, electric fuel, HHV
First online1998
Monthly net generation
EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
Capacity factor by year
Net MWh ÷ (summer MW × hours), primary-fuel units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
Heat rate by year
Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Annual data table
| Year | Net GWh | Capacity factor | Heat rate (Btu/kWh) |
|---|---|---|---|
| 2003 | 3.6 | 2.9% | 11,837 |
| 2004 | 0.8 | 0.7% | 11,486 |
| 2005 | 0 | 0.0% | — |
| 2006 | 0 | 0.0% | — |
| 2007 | 0 | 0.0% | — |
| 2008 | 0 | 0.0% | — |
| 2009 | 0 | 0.0% | — |
| 2010 | 0 | 0.0% | — |
| 2011 | 0 | 0.0% | — |
| 2012 | 0 | 0.0% | — |
| 2013 | 0 | 0.0% | — |
Generators
EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
| Gen ID | Technology | Prime mover | Nameplate MW | Summer MW | Online | Status | Planned retirement | OEM / model |
|---|---|---|---|---|---|---|---|---|
| DG-1 | Petroleum Liquids | IC | 7 | 7 | Dec 1998 | Operating (Out of service) | — | coming soon |
| DG-2 | Petroleum Liquids | IC | 7 | 7 | Dec 1998 | Operating (Out of service) | — | coming soon |
Owner / operator
Operator: Tennessee Valley Authority. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
| Tennessee Valley Authority | 100.0% | 14 MW |
Nearby plants
Within 80 km.
| Crawfish Creek Energy Storage | — | 27.3 km |
| Sand Valley Power Station | 5 MW | 41 km |
| Nickajack | 104 MW | 42.9 km |
| Albertville | 4 MW | 47.1 km |
| Chattooga Gore | 2 MW | 49.6 km |
| Guntersville | 115 MW | 53.4 km |