← Back to map

Gray Hawk Solar

Mohave County, Arizona · EIA plant ID 61272 · Operator: Gray Hawk Solar, LLC
SolarSolar PhotovoltaicBA: TEPC
Nameplate55MWSummer 55 MW
Generators1in service
Net generation137GWh12 mo to Aug 2026
Capacity factor28%solar units, summer MW
Heat rate—thermal plants only
First online2018

The 12-month figures include preliminary EIA-923 months, which EIA revises. Final data runs through Dec 2025.

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
051015GWh20192020202120222023202420252026

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2018202020222024202628.4% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201876.126.9%—
2019139.929.0%—
2020147.530.5%—
2021137.428.5%—
2022134.828.0%—
202313828.6%—
202413928.8%—
2025136.828.4%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
GHSSolar PhotovoltaicPV5555Jun 2018Operating—coming soon

Owner / operator

Operator: Gray Hawk Solar, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Gray Hawk Solar, LLC100.0%55 MW

Nearby plants

Within 80 km.
Jacobson 5 MW Solar4 MW12.2 km
La Senita1 MW16.7 km
Kingman 111 MW28.7 km
Sierra Solar—30.8 km
Kingman Energy Storage50 MW34 km
Griffith Energy LLC655 MW40.5 km