← Back to map

Conejos 1 Community Solar Array

Conejos County, Colorado · EIA plant ID 60723 · Operator: GSRP
SolarSolar PhotovoltaicBA: PSCO
Nameplate2MWSummer 2 MW
Generators1in service
Net generation4GWh12 mo to Dec 2025
Capacity factor29%solar units, summer MW
Heat rate—thermal plants only
First online2017

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0200400MWh20182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%2018202020222024202628.9% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20170.16.0%—
20183.627.6%—
20193.627.5%—
20204.131.0%—
20214.231.9%—
2022430.7%—
20234.231.8%—
20244.131.1%—
20253.828.9%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
CONEJSolar PhotovoltaicPV1.51.5Nov 2017Operating—coming soon

Owner / operator

Operator: GSRP. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Live Oak Banking Company100.0%2 MW

Nearby plants

Within 80 km.
San Luis Solar Garden1 MW14.6 km
Rock Creek 2 CSG2 MW23.7 km
Oak Leaf Solar XXX LLC (CSG)2 MW30.1 km
Alamosa53 MW30.3 km
Alamosa Solar South CSG2 MW30.4 km
San Luis Valley Regional Medical Center1 MW31 km