← Back to map

Clear Spring Ranch PV Project

El Paso County, Colorado · EIA plant ID 60511 · Operator: Madison Energy Investments LLC
SolarSolar PhotovoltaicBA: WACM
Nameplate10MWSummer 10 MW
Generators1in service
Net generation17GWh12 mo to Dec 2025
Capacity factor20%solar units, summer MW
Heat rate—thermal plants only
First online2016

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
0123GWh201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20162018202020222024202619.6% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
20162.29.8%—
20172225.1%—
201827.231.1%—
201923.827.1%—
20202427.3%—
202122.325.5%—
202222.525.7%—
202320.223.0%—
20241921.6%—
202517.219.6%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
PV1Solar PhotovoltaicPV1010Oct 2016Operating—coming soon

Owner / operator

Operator: Madison Energy Investments LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
Madison Energy Investments LLC100.0%10 MW

Nearby plants

Within 80 km.
Front Range Power Plant554 MW3.1 km
Ray D Nixon283 MW3.6 km
Palmer Solar60 MW4.8 km
Fountain Valley Power Facility228 MW5.1 km
Pike Solar Hybrid175 MW10.1 km
Carson Solar I2 MW15.4 km