← Back to map

Fiddler's Canyon 3

Iron County, Utah · EIA plant ID 59932 · Operator: SunE Solar XVII Project 3, LLC
SolarSolar PhotovoltaicBA: PACE
Nameplate3MWSummer 3 MW
Generators1in service
Net generation7GWh12 mo to Dec 2025
Capacity factor28%solar units, summer MW
Heat rate—thermal plants only
First online2015

Monthly net generation

EIA-923, all units at the plant. Net of station use; storage can go negative.
FinalPreliminary
00.250.50.751GWh2016201720182019202020212022202320242025

Capacity factor by year

Net MWh ÷ (summer MW × hours), solar units. Each year uses that year's EIA-860 ratings; the hollow dot is the latest 12 months.
0%10%20%30%20162018202020222024202628.1% · 12 mo

Heat rate by year

Electric fuel MMBtu × 1000 ÷ net MWh (Btu/kWh, HHV), fossil units only; CT + CA counted as one combined-cycle block.
Heat rate applies to fuel-burning (thermal) units only.
Annual data table
YearNet GWhCapacity factorHeat rate (Btu/kWh)
201500.0%—
20167.227.2%—
20177.227.3%—
20187.127.0%—
20196.625.1%—
20205.521.0%—
20217.127.0%—
2022726.6%—
20237.327.8%—
20247.528.4%—
20257.428.1%—

Generators

EIA-860 (annual) with EIA-860M updates through Sep 2026. EIA-923 reports generation by plant, prime mover and fuel, not by unit, so unit-level output isn't shown.
Gen IDTechnologyPrime moverNameplate MWSummer MWOnlineStatusPlanned retirementOEM / model
FID3Solar PhotovoltaicPV33Dec 2015Operating—coming soon

Owner / operator

Operator: SunE Solar XVII Project 3, LLC. Ownership shares by in-service nameplate MW (EIA-860 Schedule 4; units not listed there are wholly owned by the operator).
SunE Solar XVII Project 3, LLC100.0%3 MW

Nearby plants

Within 80 km.
Fiddler's Canyon #13 MW3.9 km
Granite Mountain Solar East, LLC80 MW4.9 km
Granite Mountain BESS East80 MW5.5 km
Iron Springs Solar, LLC80 MW5.8 km
Iron Springs BESS80 MW5.9 km
Quichapa 23 MW7.6 km